Main outputs of project cost management
Vincent is the project manager and he is involved in the cost management process to determine the budget. His manager asked him to develop the cost management plan. The main outputs of project cost management are?
A. Cost management plan, cost estimates.
B. Cost baseline, project funding requirements.
C. Cost forecasts, work performance information.
D. All of the above.
Answer: Option D is correct.
Main outputs of project cost management are:
- Cost management plan.
- Cost estimates.
- Basis of estimates.
- Cost baseline.
- Project funding requirements.
- Work performance information, cost forecasts.
- Change requests.
- Project management plan updates, project document updates.