Valid process in project quality management example
Project quality management includes the processes of incorporating organization's quality policies such as planning, managing, controlling project and product quality requirements to meet the objectives of stakeholders. Cynthia is working on the project as a project manager. She is working on the continuous improvement activities in the organization. She is working on all the 3 processes in project quality management, and she just created a quality management plan and quality metrics. One of the options given below is not a valid process in project quality management. Identify it.
A. Plan Quality management.
B. Plan Quality audit.
C. Manage Quality.
D. Control quality.
Answer: Option B is not a valid process in project quality management.
Valid processes available in project quality management are:
- Plan quality management.
- Manage quality.
- Control quality.