The main output direct and manage project work process is?

Example the main outputs of direct and manage project work

Example the main outputs of direct and manage project work Linda is the project manager and she is involved in the project integration management processes. She is involved in all the 7 processes in the project integration management. She reports to Samuel in a weak matrix organization. She is currently working in the direct and manage project work in project integration management. The main output direct and manage project work process is?  A. Work performance data. B. Issue log. C. Deliverables. D. All of the above.  Answer: Option D is correct. All the given options are correct. The main outputs of direct and manage project work in project integration management are: Deliverables. Work performance data. Issue log. Change requests. Project management plan updates, project document updates. OPA updates.

Linda is the project manager and she is involved in the project integration management processes. She is involved in all the 7 processes in the project integration management. She reports to Samuel in a weak matrix organization. She is currently working in the direct and manage project work in project integration management. The main output direct and manage project work process is?

A. Work performance data.
B. Issue log.
C. Deliverables.
D. All of the above.

Answer: Option D is correct. All the given options are correct.

The main outputs of direct and manage project work in project integration management are:

  • Deliverables.
  • Work performance data.
  • Issue log.
  • Change requests.
  • Project management plan updates, project document updates.
  • OPA updates.