The main outputs of project risk management are?

Example the main outputs of project risk management

Example the main outputs of project risk management Travis is the project manager and he is involved in the risk management process to determine the risks in the project. Individual project risks can have a positive or negative impact on the project if they occur. Project risk management identifies and manages the risks which are not addressed by other project management processes. His manager asked him to develop the risk management plan. The main outputs of project risk management are?  A. Risk management plan, Risk register. B. Project document updates, project management plan updates. C. Work performance information, change requests. D. All of the above.  Answer: Option D is correct. The main outputs of project risk management are: Risk management plan. Risk register. Risk report. Change requests. Work performance information. Project document updates, project management plan updates, OPA updates.

Travis is the project manager and he is involved in the risk management process to determine the risks in the project. Individual project risks can have a positive or negative impact on the project if they occur. Project risk management identifies and manages the risks which are not addressed by other project management processes. His manager asked him to develop the risk management plan. The main outputs of project risk management are?

A. Risk management plan, Risk register.
B. Project document updates, project management plan updates.
C. Work performance information, change requests.
D. All of the above.

Answer: Option D is correct.

The main outputs of project risk management are:

  1. Risk management plan.
  2. Risk register.
  3. Risk report.
  4. Change requests.
  5. Work performance information.
  6. Project document updates, project management plan updates, OPA updates.