Example the first step for the termination
Oftentimes when a project is terminated, senior managers will replace the project manager with an individual who is skilled in closing out projects. If this is done, the first step for the termination manager should be to—
a. Notify all relevant stakeholders of the termination
b. Complete the lessons learned report
c. Conduct an immediate review of the work packages
d. Review the status of all contracts
Answer: c. Conduct an immediate review of the work packages
The first step in attempting to improve performance
A thorough review of the work packages will provide a complete accounting of the physical progress achieved on the project. This is the first step in attempting to improve performance. [Closing]