What is Pre-assignment?

Pre-assignment

Amy is the project manager of a project that is involved in the chain grocery stores. She is working in the project resource management. Amy is reporting to Sam. She is using a technique that members of the project team selected in advance before the project started. These resources are guaranteed for the project due to their experience, skills and the project is dependent on their expertise. Identify the technique that Amy is involved in.

A. Negotiation
B. Acquisition

C. Project-staff assignments
D. Pre-assignment

Answer: Option D is correct.

Pre-assignment technique

Pre-assignment is the correct answer. In this technique members of the project team are selected in advance before the project start. Resources are guaranteed for the project due to their experience and skills. The project is dependent on their expertise.