Project exclusion case
The baseline for evaluating whether requests for changes or additional work are contained within or outside the project’s exclusion is provided by the—
a. Project management plan
b. Project scope statement
c. Project scope management plan
d. WBS dictionary
b. Project scope statement
Project exclusion identifies
Project exclusion identifies generally what is included within the project, and state explicitly what is excluded from the project, if a stakeholder might assume that a particular product, service, or result could be a project component. Project boundaries are described as part of the detailed project scope statement. [Planning]