What is WBS On project document?

Project scope baseline document

Project scope baseline document You are examining multiple scope change requests on a project you were asked to take over because the previous project manager decided to resign. To assess the degree to which the project scope will change, you need to compare the requests to which project document?   a. Preliminary scope statement  b. WBS  c. Change management plan  d. Scope management plan  Answer: b. WBS WBS The WBS, along with the detailed scope statement and the WBS dictionary, defines the project’s scope baseline, which provides the basis for any changes that may occur on the project. [Planning]

You are examining multiple scope change requests on a project you were asked to take over because the previous project manager decided to resign. To assess the degree to which the project scope will change, you need to compare the requests to which project document? 

a. Preliminary scope statement 
b. WBS 
c. Change management plan 
d. Scope management plan

Answer: b. WBS

WBS

The WBS, along with the detailed scope statement and the WBS dictionary, defines the project’s scope baseline, which provides the basis for any changes that may occur on the project. [Planning]