The change control board’s powers and responsibilities
You are implementing a project management methodology for your company that requires you to establish a change control board. Which one of the following statements best describes a change control board?
a. Recommended for use on all (large and small) projects
b. Used to review, evaluate, approve, delay, or reject changes to the project
c. Managed by the project manager, who also serves as its secretary
d. Composed of key project team members
Answer: b. Used to review, evaluate, approve, delay, or reject changes to the project
The change control board’s powers and responsibilities should be well defined and agreed upon by key stakeholders. On some projects, multiple change control boards may exist with different areas of responsibility. [Monitoring and Controlling]