Chris is the project manager for an agile project, and the project is going to be completed in another 3 months. Already the project cost overrun and it is behind the schedule. Since it is one of the key stakeholder’s interest, the project team is continuing the project. One of the given options is not valid for project trigger, which is?

Valid options are legal requirements

Chris is the project manager for an agile project, and the project is going to be completed in another 3 months. Already the project cost overrun and it is behind the schedule. Since it is one of the key stakeholder’s interest, the project team is continuing the project. One of the given options is not valid for project trigger, which is?
A. Project manager’s wish.
B. Customer request.
C. Technological advance.
D. Market demand.

Answer: Option A is not a valid option for project trigger. Valid options are legal requirements, market demand, customer request, technology and social needs.