Identify the process group that Fred is currently involved with

Fred is working on the process that the main output is the final product, final report and project document updates. Identify the process group that Fred is currently involved with

A. Direct and manage project work.
B. Develop project charter.
C. Monitor and control project work.
D. Closing.

Answer: Option D is correct. Project enters into the closing process group when the project phase is completed or the project is completed. The closing process group formally completes all the activities across all project management groups in a project phase or a project or contractual obligations. Premature closure of the project is also formally done in this process group. During project closure, the following may happen. Obtain formal sign-off from customer for the project or phase. Conduct post-project review. Measure customer satisfaction. Archive project records and documents. Document lessons learned. Update organizational project assets. Transfer products to operations. Release the team. Close the contract.