Joy is the tech lead in the organization which manufactures LCD TVs. He reports to Pamela, and she reports to the directive PMO structure. Their organization is going to start a new project soon. Pamela asked Joy to identify the stakeholders impacted by the project. Joy is reviewing one of the below documents used to identify people who are affected by the project. Identify the document.

Stakeholder register

Joy is the tech lead in the organization which manufactures LCD TVs. He reports to Pamela, and she reports to the directive PMO structure. Their organization is going to start a new project soon. Pamela asked Joy to identify the stakeholders impacted by the project. Joy is reviewing one of the below documents used to identify people who are affected by the project. Identify the document.

A. Project plan.
B. Risk register.
C. Stakeholder register.
D.WBS.

Answer: Option C is correct. Stakeholder register is used to identify the people who are affected by the project. A stakeholder register is used to identify the stakeholders involved in the project who can provide information related to the requirements. Also it contains the key requirements for the project.