Max is working in a matrix organization. Sam has worked for a couple of years in a functional organization. Now both Max and Sam are working together on a project. During their discussion, Sam has an argument with Max regarding one of the project constraints that he mentioned. As per Sam one of the choices given below is not a valid project constraint, which is?

Valid project constraints

Max is working in a matrix organization. Sam has worked for a couple of years in a functional organization. Now both Max and Sam are working together on a project. During their discussion, Sam has an argument with Max regarding one of the project constraints that he mentioned. As per Sam one of the choices given below is not a valid project constraint, which is?
A. Risk.
B. Market demand.
C. Quality.
D. Budget.

Answer. B. Market demand is not a valid project constraint. Valid project constraints are risk, quality, resources, budget, scope and schedule.