Planning is an iterative process

Joe is assigned as a project manager for an innovative project, which creates bots. Joe plans the Work to be done in the near (next) iteration is planned in detail, and the work in the future is planned at a higher level. After the customer reviewed the work, and updates are done in the product, the next iteration is planned in detail. Planning is an iterative process, and it must be done throughout the project as more information is available. This act is known as?

A. Continuous iteration.
B. Iteration planning.
C. Progressive elaboration.
D. None of the above.

Answer: Option C is correct. Planning is an iterative process, and it must be done throughout the project as more information is available is called progressive elaboration. Work to be done in the near (next) iteration is planned in detail, and the work in the future is planned at a higher level. It is called progressive elaboration.