Ralph is working as a project manager in a tight schedule project. He is using the crashing/fasttracking to compress the schedule to finish the project on time. Ralph is reporting to a PMO structure in which the level of control is high, moderate and low. Identify the PMO structure that Ralph is reporting to.

Identify the PMO structure

Ralph is working as a project manager in a tight schedule project. He is using the crashing/fasttracking to compress the schedule to finish the project on time. Ralph is reporting to a PMO structure in which the level of control is high, moderate and low. Identify the PMO structure that Ralph is reporting to.
A. Directing, supportive and controlling.
B. Directing, controlling and supportive.
C. Supportive, Directing and controlling.
D. Controlling, Supportive and directive. 

Answer: Option B is correct. The level of control is high in directive PMO Structure. The level of control is medium in controlling PMO Structure. The level of control is low in supportive PMO structure.