What activities that take place during closure of the project or phase?

Activities that take place during closure of the project 

FirstTech corporation is involved in projects that support automation. Jose is the project manager, and manages the team of 15 members in onsite as well as offshore. The project reached the closing stage. Jose is involved in the activities that take place during closure of the project or phase. Which activity is this?

A. Scope is measured against the baseline.
B. Product is handed over to the customer and they issue a formal acceptance.
C. Release the project resources from the project work, archive the lessons learnt and other documents.
D. All of the above.

Answer: Option D is correct.

Activities that take place during closure of the project or phase are:

  • Close the contract.
  • Release the team.
  • Update OPA.
  • Document lessons learned.
  • Obtain sign-off from customer.