First level of decomposition on WBS
a. Phases of the project life cycle
b. Subcomponents
c. Major deliverables
d. Project organizational units
Answer: d. Project organizational units
WBS & OBS
The WBS includes all work needed to be done to complete the project. The organizational breakdown structure (OBS) includes the organizational units responsible for completing the work. [Planning]
![First level of decomposition on WBS On the WBS, the first level of decomposition may be displayed by using all the following EXCEPT— a. Phases of the project life cycle b. Subcomponents c. Major deliverables d. Project organizational units Answer: d. Project organizational units WBS & OBS The WBS includes all work needed to be done to complete the project. The organizational breakdown structure (OBS) includes the organizational units responsible for completing the work. [Planning] First level of decomposition on WBS On the WBS, the first level of decomposition may be displayed by using all the following EXCEPT— a. Phases of the project life cycle b. Subcomponents c. Major deliverables d. Project organizational units Answer: d. Project organizational units WBS & OBS The WBS includes all work needed to be done to complete the project. The organizational breakdown structure (OBS) includes the organizational units responsible for completing the work. [Planning]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEg_XtHavNal79BZSRXOQZjPPXuUMbkVDd_9wwoHqwJ8TVR3pK92Qn7J9ljHkLNnpw4vRgaAfneaD8MIjfLdmId5H-2vX0B3f-vTLlFw4DC2RghQ9-rWNOqGsfAXWyX-ycrHICsWW8CCjOOx/w640-h368/images+%252837%2529-01.jpeg)