First level of decomposition on WBS On the WBS, the first level of decomposition may be displayed by using all the following EXCEPT—   a. Phases of the project life cycle  b. Subcomponents  c. Major deliverables  d. Project organizational units  Answer: d. Project organizational units  WBS & OBS The WBS includes all work needed to be done to complete the project. The organizational breakdown structure (OBS) includes the organizational units responsible for completing the work. [Planning]

On the WBS, the first level of decomposition may be displayed by using all the following EXCEPT— 

a. Phases of the project life cycle 
b. Subcomponents 
c. Major deliverables 
d. Project organizational units

Answer: d. Project organizational units 

WBS & OBS

The WBS includes all work needed to be done to complete the project. The organizational breakdown structure (OBS) includes the organizational units responsible for completing the work. [Planning]