Example work performance information
a. Started deliverables
b. Costs authorized and incurred
c. Progress of deliverables
d. Completed deliverables
Answer: b. Costs authorized and incurred
Work performance information
Work performance information is an output of validate scope. It emphasizes deliverables—whether or not they have started, their progress, and ones that have finished or have been accepted. [Monitoring and Controlling]
![Example work performance information Work performance information includes all the following EXCEPT— a. Started deliverables b. Costs authorized and incurred c. Progress of deliverables d. Completed deliverables Answer: b. Costs authorized and incurred Work performance information Work performance information is an output of validate scope. It emphasizes deliverables—whether or not they have started, their progress, and ones that have finished or have been accepted. [Monitoring and Controlling] Example work performance information Work performance information includes all the following EXCEPT— a. Started deliverables b. Costs authorized and incurred c. Progress of deliverables d. Completed deliverables Answer: b. Costs authorized and incurred Work performance information Work performance information is an output of validate scope. It emphasizes deliverables—whether or not they have started, their progress, and ones that have finished or have been accepted. [Monitoring and Controlling]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjENwod-DWDXaZVCQqPhuKpalV_R26D2HLY2mDGemz1cJ020WCAjvLysea7cZWfwVUglPWQ4uQFi0SUauNrsU9QjF_LfYzcCe6OjbnYnqdrE9d0faug4FcVyDaE-aHgEKrMHCUiig85hZGr/w640-h480/images+%252849%2529-01.jpeg)