What is Developing Schedule?

Develop schedule work

Plan schedule management has 6 processes available. Terrence is the project manager in the company named as Future Technologies. He has completed the schedule management processes tasks related to Define activities, Sequence activities and Estimate activity Durations. He is involved in the process of analyzing activity sequence, dependency, resource requirements, duration, and logical relationships to develop the schedule model. The process which Terrence is working on is called?

A. Control schedule.
B. Develop schedule.
C. Plan schedule management.
D. Sequence activities.

Answer: Option B is correct.

Developing schedule

Developing schedule is a process of analyzing activity sequence, dependency, resource requirements, duration, and logical relationships to develop the schedule model. Developing schedule is an iterative process. It is a process of analyzing activity sequence, dependency, resource requirements, duration, and logical relationships to develop the schedule model. Schedule tool is used mostly to develop the schedule. We need to enter the durations, schedule activities, resources, resource availability, and duration into the scheduling tool, to generate the schedule. Based on the schedule model used, we can determine the planned start and finish dates for the project activities. Approved project schedule can be used as a baseline and it is helpful to track the project progress.