WBS dictionary information
You are establishing a PMO that will have a project management information system that will be an online repository of all program data. You will collect descriptions of all work components for each project under the PMO’s jurisdiction. This information will form an integral part of the—
a. Chart of accounts
b. WBS dictionary
c. WBS structure template
d. Earned value management reports
Answer: b. WBS dictionary
WBS dictionary includes
The WBS dictionary typically includes a code of accounts identifier, a statement of work, responsible organization, a list of schedule milestones, associated schedule activities, required resources, cost estimates, quality requirements, acceptance criteria, technical references, and agreement information. [Planning]