The key inputs to the validate scope process
a. The project management plan (scope management plan and scope baseline)
b. Change requests
c. Validated deliverables
d. Requirements traceability matrix
Answer: b. Change request
Input & output
The change requests are not an input of the validate scope process but are an output. The other items are all inputs to help the project manager validate the scope of the project. [Monitoring and Controlling]