Progressive elaboration & Rolling wave planning
Jennifer is working on an agile project. And she is working on planning the iterations. Work to be done in the near (next) iteration is planned in detail, and the work in the future is planned at a higher level. The work to be done in the future planned at a higher level is called?
A. Progressive elaboration.
B. Rolling wave planning.
C. Options A and B are correct.
D. Only Option B is correct.
Answer: Option C is the right answer.
Work to be done in the near (next) iteration is planned in detail, and the work in the future is planned at a higher level and it is called rolling wave planning. Progressive elaboration is also a correct answer.
Rolling wave planning:
It uses iterative planning. Work to be done in the near (next) iteration is planned in detail, and the work in the future is planned at a higher level. It is called progressive elaboration. Agile methodologies using rolling wave planning. Only plan in detail for the current iteration and complete the work. After user reviewed the work, and updates are done in the product, the next iteration is planned in detail.
Progressive elaboration:
Planning is an iterative process, and it must be done throughout the project as more information is available. It is called progressive elaboration.