What is Rolling Wave Planning?

Rolling wave planing information

Rolling wave planing information Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done—   a. Throughout all project phases  b. For successful completion of the current project phase  c. For successful completion of the current and subsequent project phases  d. In the next project phase  Answer: c. For successful completion of the current and subsequent project phases  Rolling wave planing Rolling wave planning provides progressive detailing of the work to be accomplished throughout the life of the project, indicating that planning and documentation are iterative and ongoing processes. [Planning]

Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done— 

a. Throughout all project phases 
b. For successful completion of the current project phase 
c. For successful completion of the current and subsequent project phases 
d. In the next project phase

Answer: c. For successful completion of the current and subsequent project phases 

Rolling wave planing

Rolling wave planning provides progressive detailing of the work to be accomplished throughout the life of the project, indicating that planning and documentation are iterative and ongoing processes. [Planning]