What is Scope Baseline?

Scope Baseline Work

Bradley is working on establishing the baselines for the project. He is working on the combination of project scope statement, WBS and Work package and planning package. The baseline that Bradley is working on is called?

A. Project baseline.
B. Scope baseline.
C. Requirement baseline.
D. Product baseline.

Answer: Option B is correct.

What is Scope Baseline?

Scope baseline contains project scope statement, WBS and Work package and planning package. Once the scope is finalized and approved scope baseline is created. For future updates to the scope baseline must be approved by change control board, through the change control process.