Megan worked in a company that has a change control board to approve changes. She moved to a company in which to fix the problem, without any procedure they implement the fix in production. She created the change control board in the new company and appointed members of the board. After the board reviewed the changes the number of uncontrolled changes is reduced. The reason for uncontrolled changes that will affect the project cost, schedule, quality and also increase the risk for the project is called?

A. Gold plating.
B. Scope creep.
C. Change request.
D. Transition requirement.

Answer: Option B is correct.

Scope creep is

Uncontrolled changes and will affect the project cost, schedule, quality and also it will increase the risk for the project is called scope creep. It will increase the risk of the project.