Valid Float and Not Valid Float

Critical path method helps to find out which activities have float, and can be delayed without delaying the project schedule. Critical path has zero float, so the activities on the critical path should not be delayed. Float makes the project work flexible . One of the below options is not a valid float, identify it.

A. Free float.
B. Product float.
C. Total float.
D. Project float.

Answer: Option B is not a valid float.

Valid Float Types are;

  • Total Float: The float for an activity is the amount of time that can be delayed without impacting the project schedule. The float for the activities on the critical path is zero.
  • Free Float: The amount of time an activity can be delayed without affecting the early start of its successor.
  • Project Float: The amount of time a project can be delayed without delaying the externally imposed project completion date.