What is valid input to the monitor and control project work process ?

Valid input to the monitor and control project work process

Carol is the senior manager in the plan-driven project. She is involved in the process whereby she compares the actual performance against the planned one in the project management plan. If there is any variation from the plan, the variation is corrected through corrective action by the change control process. One of the options given below is not a valid input to this process. Identify it.

A. Project management plan.
B. Project charter.
C. Project documents.
D. Work performance information.

Answer: Option B is not a valid option.

Valid input to the monitor and control project work process are:

  • Project management plan.
  • Project documents.
  • Work performance information.
  • EEF.
  • OPA.