WBS work package
You want to structure your project so that each project team member has a discrete work package to perform. The work package is a—
a. Deliverable at the lowest level of the WBS
b. Task with a unique identifier
c. Required level of reporting
d. Task that can be assigned to more than one organizational unit
Answer: a. Deliverable at the lowest level of the WBS
The work package
A work package is the lowest or smallest unit of work division in a project or WBS. The work package can be scheduled, cost estimated, monitored, and controlled. [Planning]
![WBS work package You want to structure your project so that each project team member has a discrete work package to perform. The work package is a— a. Deliverable at the lowest level of the WBS b. Task with a unique identifier c. Required level of reporting d. Task that can be assigned to more than one organizational unit Answer: a. Deliverable at the lowest level of the WBS The work package A work package is the lowest or smallest unit of work division in a project or WBS. The work package can be scheduled, cost estimated, monitored, and controlled. [Planning] WBS work package You want to structure your project so that each project team member has a discrete work package to perform. The work package is a— a. Deliverable at the lowest level of the WBS b. Task with a unique identifier c. Required level of reporting d. Task that can be assigned to more than one organizational unit Answer: a. Deliverable at the lowest level of the WBS The work package A work package is the lowest or smallest unit of work division in a project or WBS. The work package can be scheduled, cost estimated, monitored, and controlled. [Planning]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi2s-chuXs0BtYPnDc7q3AKpJhtktao-QHa8LiM4_3kNJYdW72MBYzcyPpIlK4TBxljpmWZvTjgrqXFiPQ0_DLb3zV_RSGkXDZy2DLgJWg23B-oi16L-SIfvJuvUl61luKSgjKMHYcjQCuO/w640-h360/images+%252835%2529-01.jpeg)