When change control system
Assume that you are a major subcontractor doing work for a prime contractor on a major project. Your change control system should—
a. Be identical to that of the prime contractor
b. Follow the rigor of international configuration management standards
c. Comply with relevant contractual provisions
d. Only consider approved change requests
Answer: c. Comply with relevant contractual provisions
Complying with relevant contractual provisions
In addition to complying with any relevant contractual provisions, scope change control must be integrated with the project’s overall change control system and with any systems in place to control project and product scope. [Monitoring and Controlling]