Which of the following strongly influences how requirements are managed?
Your project is now under way, and you are working with your team to prepare your requirements management plan. Which of the following strongly influences how requirements are managed?
a. The phase-to-phase relationship
b. A set of procedures by which project scope and product scope may be changed
c. Requirements traceability matrix
d. Requirements documentation
Answer: a. Phase-to-phase relationship
Phase-to-phase relationship
The requirements management plan defines how requirements will be analyzed, documented, and managed. It is strongly influenced by the phase-to-phase relationship. The project manager selects the most effective relationship for the project and documents it in the plan. [Planning]