Point to selected and assigned
Ideally, a project manager should be selected and assigned at which point in the project life cycle?
a. During the initiating processes
b. During the project planning process
c. At the end of the concept phase of the project life cycle
d. Prior to the beginning of the development phase of the project life cycle
Answer: a. During the initiating processes
When the project manager is selected and assigned
When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization. [Initiating]