Which point in the project manager should be selected and assigned?

Point to selected and assigned

Point to selected and assigned Ideally, a project manager should be selected and assigned at which point in the project life cycle?   a. During the initiating processes  b. During the project planning process  c. At the end of the concept phase of the project life cycle  d. Prior to the beginning of the development phase of the project life cycle  Answer: a. During the initiating processes  When the project manager is selected and assigned When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization. [Initiating]

Ideally, a project manager should be selected and assigned at which point in the project life cycle? 

a. During the initiating processes 
b. During the project planning process 
c. At the end of the concept phase of the project life cycle 
d. Prior to the beginning of the development phase of the project life cycle

Answer: a. During the initiating processes 

When the project manager is selected and assigned

When the project manager is selected and assigned to the project during initiation, several of the usual start-up tasks for a project are simplified. In addition, becoming involved with project activities from the beginning helps the project manager to understand where the project fits within the organization in terms of its priority relative to other projects and the ongoing work of the organization. [Initiating]