Free float used
Several types of float are found in project networks. Float that is used by a particular activity and does NOT affect the float in later activities is called—
a. Extra float
b. Free float
c. Total float
d. Expected float
Answer: b. Free float
Free float
Free float is defined as the amount of time an activity can be delayed without delaying the early start of any immediately succeeding activities. [Planning]