In project development, schedule information such as who will perform the work, where the work will be performed, activity type, and WBS classification are examples of—
a. Activity attributes
b. Constraints
c. Data in the WBS repository
d. Refinements
Answer: a. Activity attributes
Identifying activity attributes
Identifying activity attributes is helpful for further selection and sorting of planned activities. They are used for schedule development and for report formatting purposes. [Planning]