You are managing a project to redesign a retail store layout to improve customer throughput and efficiency. Much project work must be done on site and will require the active participation of store employees who are lifelong members of a powerful union with a reputation for labor unrest. One important component of your schedule must be—
a. A resource capabilities matrix
b. Buffers and reserves
c. A resource calendar
d. A resource histogram
Answer: c. A resource calendar
Relationship between project and resource calendar
Project and resource calendars identify periods when work is allowed. Project calendars affect all resources. Resource calendars affect a specific resource or a resource category, such as a labor contract that requires certain workers to work on certain days of the week. [Planning]