The risk register
a. Define activities
b. Sequence activities
c. Estimate activity resources
d. Control schedule
Answer: b. Sequence activities
Relationship between risk register and activity sequence
The risk register may require updates in both the sequence activities and develop schedule processes. In the sequence activity process, the activity lists and activity attributes may need updates as well. [Planning]