Key input to define activities
a. Project management plan
b. Project scope management plan
c. Schedule management plan
d. Project management software
Answer: c. Schedule management plan
Schedule management plan as key input
While there are a number of inputs to define activities, the schedule management plan is a key input. It shows the level of detail necessary to manage the work. [Planning]
![Key input to define activities Which of the following is a key input to define activities? a. Project management plan b. Project scope management plan c. Schedule management plan d. Project management software Answer: c. Schedule management plan Schedule management plan as key input While there are a number of inputs to define activities, the schedule management plan is a key input. It shows the level of detail necessary to manage the work. [Planning] Key input to define activities Which of the following is a key input to define activities? a. Project management plan b. Project scope management plan c. Schedule management plan d. Project management software Answer: c. Schedule management plan Schedule management plan as key input While there are a number of inputs to define activities, the schedule management plan is a key input. It shows the level of detail necessary to manage the work. [Planning]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiwxaA_J73thYp3Rg25DA2jNYveqtgKXcoMFihZ8mSuGn2nRG4pDWqyl-bB09qlVvfHg9eOSVVtVcCZe-JRYTpV2CQNPIwyOgLs62AXb09Om9M2r1R0eqaDtyQmxyBBG_lxvl43k5DGLImR/w640-h428/images+%252883%2529-01.jpeg)