How to minimize the impact of changes on your project?

Minimize the impact of changes

Minimize the impact of changes You want to minimize the impact of changes on your project, yet you want to ensure that change is managed when and if it occurs. This can be done through each of the following ways EXCEPT—   a. Rejecting requested changes  b. Approving changes and incorporating them into a revised baseline  c. Documenting the complete impact of requested changes  d. Ensuring that project scope changes are reflected in changes to product scope  Answer: d. Ensuring that project scope changes are reflected in changes to product scope  Integrated change control Integrated change control requires maintaining the integrity of baselines by releasing only approved changes into project products, services, or results. It also ensures that changes to product scope are reflected in the project scope definition. This is done by coordinating changes across the entire project. [Monitoring and Controlling]

You want to minimize the impact of changes on your project, yet you want to ensure that change is managed when and if it occurs. This can be done through each of the following ways EXCEPT— 

a. Rejecting requested changes 
b. Approving changes and incorporating them into a revised baseline 
c. Documenting the complete impact of requested changes 
d. Ensuring that project scope changes are reflected in changes to product scope

Answer: d. Ensuring that project scope changes are reflected in changes to product scope 

Integrated change control

Integrated change control requires maintaining the integrity of baselines by releasing only approved changes into project products, services, or results. It also ensures that changes to product scope are reflected in the project scope definition. This is done by coordinating changes across the entire project. [Monitoring and Controlling]