Sequencing project activities in the schedule
a. There may be scheduled dates for specific milestones
b. Every activity is connected to at least one predecessor and at least one successor
c. Lead or lag time may be required
d. Necessary sequencing of events may be described by the activity attributes
Answer: b. Every activity is connected to at least one predecessor and at least one successor
The sequence activity process
The sequence activity process involves identifying and documenting relationships among the project activities. However, the last activity or milestone are not connected to at least one successor. [Planning]