What activities are performed when sequencing project activities in the schedule?

Sequencing project activities in the schedule

Sequencing project activities in the schedule When sequencing project activities in the schedule, all the following are true EXCEPT—   a. There may be scheduled dates for specific milestones  b. Every activity is connected to at least one predecessor and at least one successor  c. Lead or lag time may be required  d. Necessary sequencing of events may be described by the activity attributes  Answer: b. Every activity is connected to at least one predecessor and at least one successor  The sequence activity process The sequence activity process involves identifying and documenting relationships among the project activities. However, the last activity or milestone are not connected to at least one successor. [Planning]

When sequencing project activities in the schedule, all the following are true EXCEPT— 

a. There may be scheduled dates for specific milestones 
b. Every activity is connected to at least one predecessor and at least one successor 
c. Lead or lag time may be required 
d. Necessary sequencing of events may be described by the activity attributes

Answer: b. Every activity is connected to at least one predecessor and at least one successor 

The sequence activity process

The sequence activity process involves identifying and documenting relationships among the project activities. However, the last activity or milestone are not connected to at least one successor. [Planning]