The main outputs of project schedule management are?

Main outputs of project schedule management

Stacy is the project manager and she is involved in the schedule management process to develop schedule and control schedule. Her manager asked her to estimate the activity durations. The main outputs of project schedule management are?

A. Schedule management plan, activity list, and milestone list.
B. Project Schedule network diagram, basis of estimates, schedule data.
C. Duration estimates, project schedule, schedule baseline.
D. All of the above.

Answer: Option D is correct.

Main outputs of plan schedule management are:

  • Schedule management plan.
  • Activity list.
  • Activity attributes.
  • Milestone list.
  • Change requests.
  • Project schedule network diagram.
  • Duration estimates.
  • Basis of estimates.
  • Schedule baseline.
  • Project schedule.
  • Schedule data.
  • Project calendars.
  • Project management plan updates, project documents updates.
  • Work performance information. Schedule forecasts.