Project scope statement is important in scope control
a. Is a critical component of the scope baseline
b. Provides information on project performance
c. Alerts the project team to issues that may cause problems in the future
d. Is expected to change throughout the project
Answer: a. Is a critical component of the scope baseline
Key input to scope control
The project scope statement, along with the WBS and WBS dictionary, is a key input to scope control. [Monitoring and Controlling]
![Project scope statement is important in scope control The project scope statement is important in scope control because it— a. Is a critical component of the scope baseline b. Provides information on project performance c. Alerts the project team to issues that may cause problems in the future d. Is expected to change throughout the project Answer: a. Is a critical component of the scope baseline Key input to scope control The project scope statement, along with the WBS and WBS dictionary, is a key input to scope control. [Monitoring and Controlling] Project scope statement is important in scope control The project scope statement is important in scope control because it— a. Is a critical component of the scope baseline b. Provides information on project performance c. Alerts the project team to issues that may cause problems in the future d. Is expected to change throughout the project Answer: a. Is a critical component of the scope baseline Key input to scope control The project scope statement, along with the WBS and WBS dictionary, is a key input to scope control. [Monitoring and Controlling]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgdf84qwXTK_W0MzFziM8Q9oBgkcDYUgS5jd14F73pgcXM3AZd-iUdoSMcrCM8MZ6S8Z0n2_iharnkx_V4iSMtFmbzVcGmEW5nxdSIBcthNHL7-ZZzrA72yxRNPg0SBfdxV9Obg8HyoxgRe/w640-h428/images+%252858%2529-01.jpeg)