Prepare change request example
Your project is proceeding according to schedule. You have just learned that a new regulatory requirement will cause a change in one of the project’s performance specifications. To ensure that this change is incorporated into the project management plan, you should—
a. Call a meeting of the change control board
b. Change the WBS, project schedule, and project plan to reflect the new requirement
c. Prepare a change request
d. Immediately inform all affected stakeholders of the new approach to take on the project
c. Prepare a change request
Prepare a change request
The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manage project work process and an input to the perform integrated change control process. [Executing and Monitoring and Controlling]
![Prepare change request example Your project is proceeding according to schedule. You have just learned that a new regulatory requirement will cause a change in one of the project’s performance specifications. To ensure that this change is incorporated into the project management plan, you should— a. Call a meeting of the change control board b. Change the WBS, project schedule, and project plan to reflect the new requirement c. Prepare a change request d. Immediately inform all affected stakeholders of the new approach to take on the project c. Prepare a change request Prepare a change request The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manage project work process and an input to the perform integrated change control process. [Executing and Monitoring and Controlling] Prepare change request example Your project is proceeding according to schedule. You have just learned that a new regulatory requirement will cause a change in one of the project’s performance specifications. To ensure that this change is incorporated into the project management plan, you should— a. Call a meeting of the change control board b. Change the WBS, project schedule, and project plan to reflect the new requirement c. Prepare a change request d. Immediately inform all affected stakeholders of the new approach to take on the project c. Prepare a change request Prepare a change request The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manage project work process and an input to the perform integrated change control process. [Executing and Monitoring and Controlling]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi4_VXlW4qDewgt6K9mSVfBN4vbpKuQsSwVOcnDruJjXqKLRczWw0pBuqwXKmhNSLI9MxfYlK52cdjaFn2gDW3Cxd2wYKv4C8u02iILCs1IHgmL9mXLtQCAdde-Cy3yWaScU9vNOXUFPLNU/w640-h426/images+%252814%2529-02.jpeg)