What is valid processes available in project scope management?

Valid processes available in project scope management

Scope management involves the process required to ensure the project includes all the work required, and only the work required to complete the project successfully. Amanda is mostly working on project resource management and project scope management. Mainly she works with stakeholders to collect the requirements and validating the scope of the product that is developed as a result of the project. She was talking to a co-worker regarding the processes available in project scope management. She identified one of the options given below is not a valid process in project scope management, which one is it?

A. Plan scope management, collect requirements.
B. Project schedule, schedule management plan.
C. Define scope, create WBS.
D. Validate scope, control scope.

Answer: Option B is not a valid process.

Both project schedule and schedule management plan are the key outputs in project scope management.

Valid processes available in project scope management are:

  • Plan scope management.
  • Collect requirements.
  • Define scope.
  • Create WBS.
  • Validate scope.
  • Control scope.