What are example key input to the define activities process?

Example key input to the define activities process

Example key input to the define activities process Which one of the following is a key input to the define activities process?   a. Project management plan  b. Project scope statement  c. Project scope baseline  d. Project charter  Answer: c. Project scope baseline  Key input to the define activities process and are used to develop the activity list The scope baseline—made up of the scope statement, WBS, and WBS dictionary—is a key input to the define activities process and are used to develop the activity list that subsequently will help to create the schedule. [Planning

Which one of the following is a key input to the define activities process? 

a. Project management plan 
b. Project scope statement 
c. Project scope baseline 
d. Project charter

Answer: c. Project scope baseline 

Key input to the define activities process and are used to develop the activity list

The scope baseline—made up of the scope statement, WBS, and WBS dictionary—is a key input to the define activities process and are used to develop the activity list that subsequently will help to create the schedule. [Planning