Example relarionships finish to finish
You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are—
a. Start-to-finish
b. Finish-to-start
c. Start-to-start
d. Finish-to-finish
Answer: d. Finish-to-finish
The completion of the work
The completion of the work of the successor activity depends upon the completion of the work of the predecessor activity. [Planning]
![Example relarionships finish to finish You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are— a. Start-to-finish b. Finish-to-start c. Start-to-start d. Finish-to-finish Answer: d. Finish-to-finish The completion of the work The completion of the work of the successor activity depends upon the completion of the work of the predecessor activity. [Planning] Example relarionships finish to finish You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are— a. Start-to-finish b. Finish-to-start c. Start-to-start d. Finish-to-finish Answer: d. Finish-to-finish The completion of the work The completion of the work of the successor activity depends upon the completion of the work of the predecessor activity. [Planning]](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjmkzw_ToOexRpe__YiM959RcOYo3zxS4ZWeewIysk7sntokW53QrbL2EHvMybRhJYwBCwvuEDTBnRqm2QzOMg_bRzF1wbwZHGT3nQFsjrPHk8AwMEm455WJakY-xLMsV2ymRJpumVXiGNo/w640-h380/images+%252875%2529-01.jpeg)