Project schedule
Working with your team to provide the basis for measuring and reporting schedule progress, you agree to use the—
a. Schedule management plan
b. Network diagram
c. Project schedule
d. Technical baseline
c. Project schedule
Key input to project control
The approved project schedule is a key input to schedule control. It is the schedule baseline, as it is the approved version of a schedule model, and it provides the basis for measuring and reporting schedule performance. [Monitoring and Controlling]