What is the key input to project control?

Project schedule

Project schedule Working with your team to provide the basis for measuring and reporting schedule progress, you agree to use the—   a. Schedule management plan  b. Network diagram  c. Project schedule  d. Technical baseline  c. Project schedule  Key input to project control The approved project schedule is a key input to schedule control. It is the schedule baseline, as it is the approved version of a schedule model, and it provides the basis for measuring and reporting schedule performance. [Monitoring and Controlling]

Working with your team to provide the basis for measuring and reporting schedule progress, you agree to use the— 

a. Schedule management plan 
b. Network diagram 
c. Project schedule 
d. Technical baseline

c. Project schedule 

Key input to project control

The approved project schedule is a key input to schedule control. It is the schedule baseline, as it is the approved version of a schedule model, and it provides the basis for measuring and reporting schedule performance. [Monitoring and Controlling]