Project schedule example
Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You are working with your team to define how to manage schedule changes. You documented your decisions in which of the following?
a. Schedule change control procedures
b. Schedule management plan
c. Schedule risk plan
d. Service-level agreement
Answer: b. Schedule management plan
Schedule management plan
The schedule management plan is part of the overall project management plan and defines, among other things, how schedule changes will be managed. Whether it is formal or informal, highly detailed or broadly framed, it generally is based on specific project needs. [Planning]