Schedule Performance Index Case
a. Project is running behind the monetary value of the work it planned to accomplish
b. Earned value physically accomplished thus far is 100%
c. Project has experienced a permanent loss of time
d. Project may not be on schedule, but the project manager need not be concerned
Answer: a. Project is running behind the monetary value of the work it planned to accomplish
SPI represents
The SPI represents how much of the originally scheduled work has been accomplished at a given period in time, thus providing the project team with insight as to whether the project is on schedule. [Monitoring and Controlling]